US contractor McDermott Worldwide has delivered with completion of its first subsea engineering, procurement, development and set up contract with Santos on the producing Bayu-Undan fuel subject offshore Timor-Leste.
McDermott’s workscope for the Bayu-Undan infill properly Section 3C challenge concerned a tie-back of a single in-field properly to current amenities and included flushing to clear hydrocarbons, reusing current versatile flowlines, plus a brand new umbilical and related infrastructure.
The restoration and reuse of current versatile flowlines was a major consider enabling the work to be accomplished 9 months from award and inside the challenge schedule, famous McDermott.
In step with the contractor’s and Santos’ sustainability targets, native Timor-Leste companies had been engaged to execute elements of the challenge, together with concrete mattress manufacture, marine coaching and expertise onboard the first set up vessel — the lay vessel 108.
“McDermott accomplished the scope inside 9 months of award,” mentioned Mahesh Swaminathan, McDermott’s senior vice chairman, Asia Pacific, subsea and deepwater.
“Our industry-leading well being, security and environmental protocols had been efficient in mitigating sure dangers related to executing a subsea EPCI scope in the course of the Covid-19 pandemic.”
Australian operator Santos’ Bayu-Undan subject is situated roughly 500 kilometres off the northwest coast of Darwin, Australia, and 200 kilometres off the southeast coast of Timor-Leste.