ISLAMABAD – The chief board of the Nationwide Freeway Authority on Wednesday shaped a committee to resolve the difficulty of an out of date Composite Schedule Price (CSR), which is hindering the procurement course of at a big scale.
The CSR means worth schedules for numerous gadgets utilized in highway tasks duly permitted by the board for making ready value estimates of contracts for civil works and it ought to be up to date with the passage of time to align it with market charges.
Nevertheless, within the case of NHA, its CSR-2022 relies upon outdated market charges of September 2021 and charges talked about in opposition to completely different gadgets in it are fairly beneath then the present market because of unprecedented worth hike lately.
Sources stated that the out of date CSR resulted in fairly excessive bids within the latest months and a lot of the tenders have been awarded on a really increased facet as in comparison with the precise engineer’s estimates, which was based mostly on the CSR- 2022 and was not market appropriate.
The figures not solely perturbed the circles inside NHA however as per the sources an anti-corruption watchdog additionally stepped into the matter and dragged the officers, resultantly the procurement was halted until a closing resolution on this regard.
NHA’s govt board in its final assembly deliberated was knowledgeable that the tender acceptance committee had accepted such excessive bids and awarded contracts with the understanding that the CSR can be revised however draft CSR- 2023 is but to be permitted by the board.
The board was apprised that if the excessive bids acquired are evaluated as per the draft CSR-2023 then they turn into justifiable however evaluating each bid on market charges with out having a lawful backing is a tough activity and it might appeal to some issues in future.
The board was additionally knowledgeable that on account of delay in approval of CSR- 2023, a number of works of essential nature are being delayed that might lead to additional damages to the highway community the place intervention is required in addition to enhance in the associated fee.
The board was requested to look into the matter and a coverage resolution was solicited on this regard however the govt board has shaped a three-member committee comprising member planning, member finance and member engineering coordination to deliberate upon this matter and give you a complete resolution within the subsequent assembly.
A consultant of the Contractor Affiliation of Pakistan whereas responding on the difficulty maintained that the CSR-2022 is completely unjustified and charges are outdated.
He strongly demanded that the revised CSR ought to be permitted instantly to cater the market wants.