Dr Wee Ka Siong, Malaysia’s Transport Minister, stated on Monday (March 14) that progress on the Johor Bahru-Singapore Speedy Transit System (RTS) Hyperlink is at almost 10 per cent. The Minister made this comment in a speech in Parliament.
“Presently, the progress of labor for the RTS mission has reached virtually 10 per cent, the place the land acquisition course of has already been accomplished and the infrastructure design has additionally been finalised,” he stated, including,“At present groundwork, motion of utilities and piling works are underway.”
The groundbreaking ceremony for the RTS Hyperlink connecting Singapore to Johor was held on Nov 22 of final yr. The mission is ready to chop journey time between the 2 neighbouring areas to 5 minutes.
The hyperlink will join Bukit Chagar station in Johor Bahru to Woodlands North station in Singapore.
The hyperlink is perceived to be an essential answer to persistent site visitors issues on the Causeway between Singapore and Malaysia, which is utilized by round 300,000 folks every day, nearly all of whom are Malaysians who commute to Singapore to work.
The RTS hyperlink has the capability to move round 10,000 passengers every manner, which might serve to drastically reduce site visitors congestion issues on the Causeway.
The mission is budgeted to value RM10 billion (S$3.24 billion). Malaysia shall be offering RM3.716 billion for the mission. Singapore will shoulder the remaining 61 per cent.
In response to Malaysia Speedy Transit System (MRTS) chief government Mohd Zarif Hashim, “Forty per cent of the whole infrastructure development value shall be allotted to Bumiputera contractors, together with these from Grade 1 to Grade 6 from Johor.”
Dr Wee has additionally stated that development will happen in two phases, the primary being the event and civil section that can happen from 2021 to the tip of 2024, after which the commissioning and testing section, which can happen from 2025 by the tip of 2026.
Dr Wee additionally stated in his speech that the Malaysian Transport Ministry is making ready for preliminary discussions with Singapore relating to reviving the terminated KL-Singapore Excessive-Pace Rail (HSR) mission within the subsequent few months.
– Commercial 2-
CNA quotes the Minister as saying, “As for the HSR Venture, MOT has been given the accountability to provoke discussions with the Authorities of Singapore on the brand new phrases, and discussions are nonetheless at an early stage.
At this level, the ministry is ready to carry preliminary talks with Singapore within the second quarter of this yr,” he added. /TISG